Five Mile Station
Civil / Site Work
Drilling for 30” x 12’ deep pier
foundation
Five Mile Station
Project was based in Humphrey, NY. This was a new build substation for National Grid. Work consisted of stripping the site and using a cut/fill of more than 6 feet, installing nearly 300 drilled pier foundations, oil containment system, ground grid, cable trench, final yard stone and all site restoration of project while maintaining compliance with the mandates of Article 7.